Indian Railways has successfully completed the construction of a 4,185-metre-long tunnel—its longest ever in Odisha—on the Khurda Road–Balangir rail line. Known as Tunnel T-4, the structure lies between Adenigarh and Charichhak stations in Boudh district.
“A major milestone in the Khurda Road–Balangir New Rail Line project was achieved on April 16 with the successful breakthrough (daylighting) of Tunnel T-4,” the Railways said in an official statement.
Odisha’s longest rail tunnel (4.185 km) is now live! Built with NATM through tough clay-pebble strata, an engineering masterpiece ,T4 will link Western Odisha to BBS under the strategic Khurda Road–Balangir Rail project.#TunnelT4 #KhurdaBalangirRail #ECoRupdate @RailMinIndia pic.twitter.com/5juCUAesTY
— East Coast Railway (@EastCoastRail) April 16, 2025
So far, 226 km of the 301 km-long Khurda Road–Balangir line has been commissioned. Operational stretches include Khurda Road to Daspalla on one end, and Balangir to Purnakatak on the other.
The remaining 75 km segment—from Daspalla to Purnakatak—remains under construction. This includes seven tunnels, with T-4 being the longest and most significant. The breakthrough of Tunnel T-4 marks a major step forward for the project, which aims to link Odisha’s coastal belt with its western interior.
Once complete, the line is expected to enhance connectivity, promote regional integration, and spur economic development across the state.
You may also like
Deoband-Roorkee rail line approved, cuts Delhi-Dehradun distance by 40 km
'Curse me': Anurag Kashyap begs 'kingpins of sanskar' to leave his daughter alone, amid backlash against comment in Brahmins
Vaishakh Tips: Is the family facing domestic strife and financial crisis? Do observe this fast in Vaishakh! You will get 1000 times benefit..
IPL 2025: The Way Nehal Wadhera Batted Was Commendable, Says Harpreet Brar After Win Over RCB
Another 100 seized vehicles gutted. Why is Delhi Police's Wazirabad yard on fire again?